Australia’s New South Wales sets 16GW of renewables by 2030 target

Facebook
Twitter
LinkedIn
Reddit
Email
ASL said New South Wales currently has more than 50GW of proposed generation plants in various development stages. Image: GRS Energy.

Australia’s New South Wales has increased its renewable energy targets to 16GW of new clean power generation by 2030 and 42GWh of long-duration energy storage (LDES) by 2034.

In its role as the New South Wales Consumer Trustee, AusEnergy Services Limited (ASL), formerly known as AEMO Services, has released revised targets for LDES and renewables in its 2025 Infrastructure Investment Objectives (IIO) Report and the inaugural NSW Generation Investment Outlook (NSW GIO).

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Indeed, according to ASL, the original legislated minimums, which stood at 12GW for clean power and 28GWh for LDES, would result in excessive electricity prices as the state transitions away from coal-fired generation, with 10GW set to be retired by 2035.

As such, the group has increased the targets by 33% for clean power generation and 50% for LDES.

ASL CEO Nevenka Codevelle said these revised targets are a “call to action – for more energy infrastructure to be delivered, sooner.”

“What we’re finding now is that to maximise consumer benefits, we need to target a greater infrastructure build both before and after 2030,” Codevelle added.

More than 50GW of generation plants in development

New South Wales has made substantial progress toward its renewable energy objectives. ASL states that the total capacity of constructed or secured generation infrastructure represents approximately 76% of the 2030 minimum objective.

ASL adds that New South Wales currently has more than 50GW of proposed generation plants in various development stages, including 12.5GW of projects with secured development approval.

This indicates that sufficient capacity potential exists, but challenges remain in accelerating project timelines. The IIO report acknowledges that meeting the new, more ambitious targets will require “an unprecedented level of support and coordination to reduce lead times and fast-track the commissioning of new capacity.”

As previously reported by PV Tech, New South Wales topped the rankings for the most attractive state for clean energy and energy storage investment in Australia. The state dethroned its northern neighbour, Queensland, following its turbulent start to the year after the success of the Liberal National Party (LNP) of Queensland, under the leadership of David Crisafulli, in the 2024 election.

Despite this, advocacy and engagement platform Clean Energy Investor Group (CEIG) cited several barriers as holding back further investment in New South Wales.

These include inconsistent planning requirements and delays, slow and complex Renewable Energy Zone (REZ) access, and uncertain coal closure timelines, which foster uncertainty.

Solar and wind to reach equal capacity by 2030

According to the IIO report, which aims to guide the state’s energy transformation under the Electricity Infrastructure Roadmap, large-scale solar PV and wind are expected to reach approximately 10GW of installed capacity each in New South Wales by 2030.

From 2030 to 2035, wind capacity is projected to double to approximately 20GW, while large-scale solar is projected to grow to approximately 13GW.

Although wind generation is set to scale dramatically in the next decade, the report notes that solar hybrid projects are gaining significant traction in the development pipeline. 

For example, the report emphasises recent tender results that show the increasing significance of solar hybrids, including over 1GW of solar hybrid projects awarded under the first tender of the Capacity Investment Scheme.

Meanwhile, to support the ambitious development pathway for LDES project in New South Wales, ASL has outlined a Long-Term Energy Service Agreement (LTESA) generation tender plan consisting of four 7,000GWh per annum tenders across 2026-27, followed by annual tenders amounting to 4,600GWh per annum each year from 2028.

Our publisher, Solar Media, will host the Battery Asset Management Summit Australia 2025 on 26-27 August in Sydney. You can get 20% off your ticket using the code ESN20 at checkout.

Read Next

August 26, 2025
ABO Energy has closed its first syndicated loan agreement worth €240 million (US$279.8 million) to develop and construct more wind, solar and storage project.
August 26, 2025
Investment in utility-scale solar fell by 19% in the first half of 2025, as global investment in all renewable energy projects grew by 10%.
August 26, 2025
Jakson Engineers is investing over INR80 billion (US$912.5 million) to set up a 6GW integrated solar module, cell, and wafer plant.
August 26, 2025
India installed 14.3GW of new utility-scale solar capacity in the first half (H1) of 2025, marking a 49% increase year-on-year.
August 26, 2025
The Australian Government’s CER approved 56 new power stations, with 797MW of renewable energy capacity, in July this year.
August 26, 2025
China has added 11.04GW of solar PV capacity in July 2025, a 48% decrease from the same period a year ago, according to data from China's National Energy Administration.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
September 16, 2025
Athens, Greece
Solar Media Events
September 30, 2025
Seattle, USA
Solar Media Events
October 1, 2025
London, UK
Solar Media Events
October 2, 2025
London,UK
Solar Media Events
October 7, 2025
Manila, Philippines